Gracon rehabilitated a 38′ x 48′ tainter gate trunnion hub assembly at John Redmond Dam. Our work on the project involved using a crane from the top of the dam to lower scaffolding and install a steel beam to hold the lifted gate. During the project, Gracon overcame challenging weather conditions and was able to safely and successfully complete the project.
October 2016
May 2017
Army Corps of Engineers
Burlington, Kansas