Project Sector | Manufacturing
Location | Medina, OH
Medina Downtime 3
Private Client, $9M, 8 months
Gracon retrofitted an operating asphalt shingle facility to increase capacity and add a new production line — all while the plant stayed in operation. The team installed a new steel support structure inside the facility to support new production equipment, along with new concrete foundations and underground plumbing, carefully phasing the work with the client’s production team to keep both project staff and plant personnel safe around live operations. The scope also included installing new asphalt tanks on the building’s exterior, which required relocating utilities and working around active electrical, steam, and hot asphalt piping. With a hard in-service deadline, incomplete engineering at the project’s start, and delayed equipment deliveries, the team leaned on significant overtime and extra planning to finish on time.